2022 Hurricane Dorian Beach Restoration Project


Sand fencing installation in south Nags Head August 16, 2019.

A beach restoration project in the summer of 2022 will replace sand lost during 2019's Hurricane Dorian. The project will place 567,000 cubic yards of sand on 4.45 miles of Nags Head's beach in the southern part of the town, from 8031 South Old Oregon Inlet Road (Comfort Inn South) near Mile Post 16, south to 10435 South Old Oregon Inlet Road (see map below).

The project is engineered to provide enough healthy, protective beach to allow the Town to align its regularly scheduled beach nourishment maintenance with those of the other northern beaches, tentatively planned for 2027. 

The dredging contractor will likely provide a preliminary schedule for the work in the spring of 2022. These projects are complex, with a lot of variables that may impact the construction schedule. 

A construction schedule map will be posted on this site in the spring of 2022. This map will be updated daily during the project to provide the latest beach closure information. 

View videos from our 2019 beach nourishment project to get a better idea of what construction entails.

Frequently Asked Questions About Beach Nourishment Construction

2022 Hurricane Dorian Beach Restoration Project Financing

The estimated $13,952,137 restoration project cost will be funded by a FEMA/North Carolina disaster assistance grant of $12,063,269, a North Carolina Department of Environmental Quality, Division of Water Resources Coastal Storm Damage Mitigation grant of $1,408,247, and a contribution of approximately $480,480 from the Town of Nags Head’s beach nourishment capital reserve.

  1. Latest Beach Nourishment Updates

    Stay up to date on Nags Head's summer 2026 beach nourishment project. Read on...
View All News

Beach Nourishment Financing/Taxes

Beach nourishment maintenance projects, as opposed to storm restoration projects, are typically financed through a combination of town-wide property taxes, including revenues from municipal service districts, and a contribution from Dare County. However, FEMA and the State of North Carolina may provide funds to replace sand lost as a result of a federally-declared disaster, such as a large hurricane.

Beach Nourishment Maintenance Project Financing/Taxes

Web Site Image Beach Nourishment Easement 2

Beach Nourishment Easements

If your oceanfront property lies south of 8827 South Old Oregon Inlet Road or between 2919 South Virginia Dare Trail and 5317 South Virginia Dare Trail, we need a beach nourishment easement signed to place sand on the beach in front of your home. Learn more on our beach nourishment easement web page.