Outer Banks Shoreline Management - Nags Head Summer 2019

Dredge Liberty Island In Norfolk for Repairs

The Dredge Liberty Island is in Norfolk today for additional repairs. We expect the dredge to return to work on Monday, July 8. You can track the dredge's whereabouts at MarineTraffic and search for Liberty Island. 

Once the dredge returns, construction will continue to progress north to tie into the already completed beach near Mile Post 14. After the tie-in is completed, hopefully on Monday or Tuesday, construction will progress south from the subline about 5,000 feet. 

The Forrest Street public beach access near Mile Post 15.5 remains closed to parking, however pedestrians may still use the access.

Progress Map